The works to build Cameleon’s third 
The house will be built on 
• Building 1: Foster house: dormitories and bathrooms for children, rooms for the supervising staff and the founder, living room, canteen and kitchen, study room, therapy room, 
• Building 2: Offices of the Director, administrative and financial staff, meeting room, media library, clinic, 
• Outbuildings: 
Below are some pictures showing the construction of this new 
• Building 1
From March to July 2018, works are going well: dining room, entrance, girls dormitories, Director’s room, staff room and therapy room. Everything is almost done and will be ended by late October.
 
			March 2018
Digging and start of the foundations
 
			April 2018
Foundations
 
			June 2018
Construction of walls, plumbing works and finishing touches on walls
 
			July 2018
Concrete floor preparation and 
 
			August 2018
Final touches on walls and installation // Welding of the steel frame
 
			September 2018
Roof setup and floor tiling in the entrance
 
			Building 1 when ended
• Building 2
Office and clinic’s construction works were kicked off in June 2018 and will be ended by late March 2018.
.
 
			June 2018
 Delimitation of the construction space dedicated to the office and the clinic, start of the foundations
 
			July 2018
Start of the construction of walls and concrete floor screeding
 
			September 2018
Final touches on the walls
 
			Building 2 when finished
• Outbuildings
Last but not least, the construction of the Mariposa hall, the laundry, the guardian’s guard station, the car park and the access road will be kicked off in September 2018 and will be ended by late March 2019.
Official opening scheduled in April 2019 and arrival of 20 girls in May 2019! In the meantime, CAMELEON, will regularly report on the works’ progresses.
 
					 
												 
					
				 
					
				 
					
				 
					
				 
					
				